Hornell, New York, June 18, 2026, 14:01 EDT
- NYSEG, part of Avangrid, wrapped up upgrades to almost 13 miles of high-voltage transmission lines in Allegany and Steuben counties ahead of schedule by three months.
- Avangrid said its Line 932 project cost less than planned, with savings to New York ratepayers topping $2 million.
- Timing is key as regulators in New York continue to review final rates for NYSEG and RG&E. The state’s grid operator has warned margins are tightening as demand picks up.
Avangrid’s New York State Electric & Gas wrapped up its transmission-line upgrade in western New York faster and cheaper than planned. The utility landed the project under budget and ahead of schedule, offering some relief on cost controls as regulators look at its rates and capital spending.
NYSEG finished its Line 932 project in Allegany and Steuben counties, covering almost 13 miles of high-voltage lines. The work started last September and wrapped up in May, three months early. NYSEG and 13 IBEW Local 10 lineworkers did the job.
The project comes as the New York Public Service Commission in May approved temporary rates for NYSEG and Rochester Gas and Electric, both Avangrid utilities. The rates were much lower than what the companies wanted, with the commission saying it will set final rates in the coming months.
New York’s grid is under more pressure, with electrification, big power projects and older assets straining the system. The New York Independent System Operator, in its 2026 Power Trends report, said reliability margins are getting tighter as demand grows.
NYSEG swapped out 58 old structures along 12.8 miles of line. Parent Avangrid said the work will help reliability and resiliency, and also set up for a power flow control device near Hornell’s Bennett Substation. That device is designed to regulate voltage and direct electricity on the local grid.
Avangrid CEO Jose Antonio Miranda said in a company release the work was an example of “smart, efficient investments that strengthen the grid.” Roman Cefali, business manager for IBEW Local 10, said the project showed the “best qualities of union labor” and gave apprentices needed field experience. Business Wire
Avangrid gets a modest win here. The 12.8-mile rebuild isn’t a big move for the company, but wrapping up ahead of schedule and cutting costs helps NYSEG as it talks with regulators about keeping up spending on reliability.
NYSEG’s Powering New York program has finished its first big job with Line 932. Avangrid says it wants to upgrade 25 substations and 420 miles of high-voltage lines as part of the plan, but a number of projects are still in the pipeline and need signoff from the state Public Service Commission.
The main risk is there. Regulatory review will shape the rest of the buildout, and ratepayers still face pressure between investment needs and bill impacts. PSC Chair Rory Christian said last month New York is looking for “strict fiscal discipline” from utilities, but it also wants to keep the lights and heat running. Department of Public Service
NYSEG isn’t the only one ramping up. Joint Utilities of New York shows that Con Edison and National Grid both have ongoing capital investment plans, along with NYSEG/RG&E. New York’s grid-spending cycle remains wide, not just focused on Avangrid’s upstate area.
Avangrid finished the line and kept costs under budget, giving the local grid a better shot at adding new generation. The company has a tangible win, but how regulators rule from here will shape its impact on broader rate issues.