NEW YORK, July 30, 2026, 11:01 a.m. EDT – Shares in IREN NASDAQ:IREN jumped 26% after the company outlined a 5GW AI roadmap, reigniting discussion about its valuation.
- Shares of IREN advanced 26.3% to $37.03 during morning trading. TeraWulf NASDAQ:WULF was up 18.2%, and Applied Digital NASDAQ:APLD increased by 19.6%.
- IREN’s 2026 revenue goal suggests annual revenue exceeding $8.3 million for each reported megawatt.
- The rate is about 3.5 times higher than TeraWulf’s Anthropic lease and five times that of Applied Digital’s most recent similar lease.
Shares of IREN Ltd NASDAQ:IREN jumped 26.3% on Thursday morning, bouncing back after a 13.6% drop the previous day. AI infrastructure stocks rallied with gains seen across the wider technology sector.
The advance was not enough to offset losses from July. IREN, TeraWulf, and Applied Digital started Thursday having fallen more than 30% over the past month.
Shares of Microsoft NASDAQ:MSFT climbed roughly 15% following its outlook, which alleviated worries over AI expenditure. The Nasdaq Composite added 2.2%, and the Philadelphia semiconductor index advanced 6.7%.
| Security | Delayed price | Thursday move | Prior one-month move |
|---|---|---|---|
| IREN | $37.03 | up 26.3% | down 33% |
| TeraWulf | $17.84 | up 18.2% | down 38% |
| Applied Digital | $27.78 | up 19.6% | down 36% |
| Global X Data Center & Digital Infrastructure ETF (NASDAQ:DTCR) | $27.63 | up 4.0% | down 13% |
Prices reflected a delay until roughly 10:46 a.m. EDT. Changes for the month were logged in Wednesday’s trading session.
IREN shares also recovered after updated remarks from co-CEO Daniel Roberts, who stated that demand is outpacing buildable capacity and confirmed that 85% of the 2026 target remains under contract.
The key differentiator for investors is revenue density. IREN aims for over $4 billion in annualized run-rate revenue (ARR) by year’s end, with a total of 480 megawatts in gross AI cloud capacity.
That amounts to over $8.3 million per revealed megawatt. The Anthropic agreement by TeraWulf suggests roughly $2.37 million per megawatt, while Applied Digital’s Delta Forge 2 lease points to $1.65 million.
| Company | Disclosed economics | Capacity basis | Approximate annual revenue per MW | Business model |
|---|---|---|---|---|
| IREN | ARR of over $4 billion in 2026 | 480 MW gross | Above $8.33 million | Managed GPU cloud |
| TeraWulf | $19 billion across 20 years | 401 MW critical IT load | $2.37 million | AI infrastructure lease, long-term |
| Applied Digital | $5.2 billion spanning 15 years | 210 MW critical IT load | $1.65 million | Take-or-pay data center lease |
The comparison is intended as directional rather than directly equivalent. IREN provides figures for gross capacity and runs the GPU cloud stack. In contrast, both peers report critical IT load under leases characteristic of property arrangements.
The increased revenue goal is due to this stack. IREN provides managed compute, storage, orchestration, and customer support, instead of just offering powered data-center space.
The move also brings greater execution risk. ARR is not recognized as revenue according to generally accepted accounting principles. It relies on GPU delivery, commissioning, testing, customer approval, usage, and pricing.
On July 20, Roberts stated the platform was “scaling at pace.” IREN expanded from around 3 MW to 480 MW provided this year, and aims to reach 1.2 GW by 2027. IREN
| Development stage | Disclosed capacity | Increase | Current description |
|---|---|---|---|
| Roughly 12 months before | About 3 MW | Base level | AI cloud capacity built in-house |
| End-2026 goal | 480 MW | 160-fold | In progress |
| Target for 2027 | 1,200 MW | 2.5x 2026 | Ongoing scale-up efforts |
| Long-term plan | 5,000 MW | 10.4x 2026 | Worldwide capacity and site pipeline |
The 5 GW target is still classed as a strategic pipeline rather than active capacity. In May, NVIDIA NASDAQ:NVDA committed to backing deployments across this pipeline through its AI infrastructure architecture.
With a market capitalisation of $12.36 billion on Thursday, IREN was valued at less than 3.1 times its declared ARR goal. Factoring in the 85% contracted proportion results in over $3.4 billion, indicating a market-cap-to-contracted-ARR multiple of under 3.7 times.
IREN’s funding buffer is significant. As of June 30, the company disclosed preliminary, unaudited cash holdings of $7.6 billion. This total comprises $1.7 billion reserved specifically for financing linked with its contract with Microsoft. Approximately 45% of the related GPU capital expenses were paid in advance by recent clients.
Delivery and funding continue to be where most risks are focused. Delays in construction, reduced utilization rates, reliance on a small number of customers, or high costs of capital may further increase the difference between ARR and recognized revenue. The 5 GW roadmap provides limited room for error.
Thursday’s action shifts sentiment but does not alter execution. A lasting re-rating requires turning IREN’s increased revenue-per-megawatt approach into cash flow while avoiding significant dilution.
