Today: 9 April 2026
Georgia Power’s $16.3B AI data-center power push leans on gas, putting bills under the microscope

Georgia Power’s $16.3B AI data-center power push leans on gas, putting bills under the microscope

NEW YORK, December 30, 2025, 08:57 ET

  • Georgia regulators approved Georgia Power’s plan to add roughly 10,000 megawatts of new generation aimed largely at data centers.
  • The buildout is priced at $16.3 billion to construct, with debate centered on who ultimately bears long-term costs.
  • Natural gas would supply most of the added capacity, alongside solar and battery storage.

Georgia Power plans a $16.3 billion construction program to add about 10,000 megawatts of generation in Georgia, much of it to serve fast-growing data centers, after state regulators approved the expansion. The company says the additions would lift its power capacity about 50%. “Large energy users are paying more so families and small businesses can pay less, and that’s a great result for Georgians,” CEO Kim Greene said. The North State Journal

The plan lands as utilities across the United States scramble to keep up with electricity demand tied to artificial intelligence. Data centers — warehouses of servers that run around the clock — require large, steady power supplies and can force utilities to build new plants years before all demand is fully locked in.

In Georgia, the flashpoint is how much of the cost lands on households that are not building the data centers. Georgia Power and regulators say the agreement includes guardrails: the average residential customer would see about $8.50 a month in savings from 2029 through 2031, and the utility would backstop the new spending through at least 2031, according to FOX 5 Atlanta. “Downward pressure” means bills are projected to be lower than they otherwise would be, not necessarily that they fall. FOX 5 Atlanta

Consumer and environmental advocates argue those protections are temporary compared with the decades it can take to pay off gas-fired plants. They say customers could still be exposed if data center demand does not arrive as forecast, or if costs rise after the agreement’s protections expire.

Georgia Power’s resource mix leans heavily on natural gas, with roughly 60% of the new capacity expected from gas-fired plants and the rest from solar and battery storage, the Atlanta Journal-Constitution reported. The company also points to longer-term emissions goals, saying it has cut greenhouse-gas emissions from its plants by more than 60% since 2007 and that parent Southern Co. has a net-zero emissions goal for 2050. ajc

The Southern Environmental Law Center, which opposed the deal, said the approval clears the way for five new methane gas plants and warned customers could pay $50 billion to $60 billion over the life of the resources. The group said building long-lived gas units could leave ratepayers exposed to fuel-price swings and shifting policy over time. Southern Environmental Law Center

Utilities often describe gas, coal and nuclear units as “dispatchable” generation — plants that can adjust output to match demand — while solar output fluctuates without storage. That distinction has become central to the data center debate, where operators want round-the-clock power and fast connections.

Supporters of Georgia Power’s buildout argue the state needs to stay ahead of demand to avoid shortages and to keep attracting investment. Critics argue the same logic can lead to overbuilding if tech firms slow construction or move projects, leaving customers to pay for underused assets.

Other power providers are also racing to secure supply for data-center growth. NextEra Energy and Google Cloud said this month they will develop new U.S. data center campuses backed by new power plants, and NextEra said it expects to announce new natural-gas-fired power deals for data centers in the next 12 to 24 months. Reuters

For regulators, the hard question is timing: build too late and the grid strains; build too early and customers pay for capacity that may sit idle. That tension has sharpened as data-center load forecasts have grown faster than traditional planning cycles.

Georgia Power can now move into project development, contracting and permitting under the approved framework. The larger fight — over future rate cases, cost recovery and whether demand matches forecasts — will play out over the next several years.

Stock Market Today

  • Notable Options Trading Activity in INTU, LRCX, SANM on Thursday
    April 9, 2026, 5:11 PM EDT. Thursday saw significant options trading volume in Intuit Inc (INTU), Lam Research Corp (LRCX), and Sanmina Corp (SANM), key components of the Russell 3000 index. INTU's options totalled 15,526 contracts, nearly 54.4% of its average daily share volume, with high activity on the $370 call expiring April 2026. LRCX options reached 53,078 contracts, some 51.9% of average daily volume, led by the $237.50 put expiring the same date. SANM saw 3,419 contracts traded, about 51.6% of its average, highlighting the $150 call for April 2026. This notable activity reflects heightened trader interest ahead of next year's April expirations.

Latest article

Tesla Revives Cheaper EV Push With New Compact SUV as Sales Pressure Builds

Tesla Revives Cheaper EV Push With New Compact SUV as Sales Pressure Builds

9 April 2026
Tesla is developing a lower-cost compact SUV, with initial production planned for Shanghai, Reuters reported Thursday. The company built 408,386 vehicles and delivered 358,023 in the first quarter, leaving its widest gap in at least four years. Reuters said the new SUV likely will not reach production this year. Tesla did not respond to questions about the project.
NIO ES9 Price Starts at 528,000 Yuan as Flagship SUV Bet Faces China EV Slump

NIO ES9 Price Starts at 528,000 Yuan as Flagship SUV Bet Faces China EV Slump

9 April 2026
NIO opened pre-orders for its ES9 flagship SUV Thursday, pricing it at 528,000 yuan with battery or 420,000 yuan under its Battery-as-a-Service plan. March deliveries rose 136% year-on-year, but NIO’s U.S. shares fell 4.9% after the announcement. The ES9 enters a shrinking premium SUV market in China, competing with Li Auto and Aito. CEO William Li warned chip shortages could add up to 10,000 yuan per vehicle.
Plug Power Stock Climbs After 2026 Profit Push, Up to $200M Cost-Cut Plan

Plug Power Stock Climbs After 2026 Profit Push, Up to $200M Cost-Cut Plan

9 April 2026
Plug Power shares rose 2.5% to $2.715 Thursday after the company reaffirmed its target of positive EBITDAS by end-2026 and projected up to $200 million in savings from Project Quantum Leap. The update followed a major electrolyzer project win in Quebec and investor meetings in Toronto and Montreal. Plug reported 2025 revenue of $710 million and a fourth-quarter gross profit of $5.5 million.
Oil Prices Today: Brent, WTI Rebound as Fragile Iran Ceasefire Leaves Hormuz Choked

Oil Prices Today: Brent, WTI Rebound as Fragile Iran Ceasefire Leaves Hormuz Choked

9 April 2026
Oil prices rebounded Thursday as traffic through the Strait of Hormuz stayed below 10% of normal, with just seven ships passing in 24 hours. Brent crude rose 1% to $95.65 a barrel, while U.S. WTI climbed 3.2% to $97.39. North Sea Forties crude hit a record $146.43. Major shippers and banks warned supply disruptions could persist for weeks despite the U.S.-Iran ceasefire.
Natural Gas Price Today: Europe’s TTF Holds Near €44 as EU Says Supply Is Safe for Now

Natural Gas Price Today: Europe’s TTF Holds Near €44 as EU Says Supply Is Safe for Now

9 April 2026
European natural gas prices hovered near 44 euros per megawatt hour Thursday after a 15% drop in the Dutch TTF benchmark. Brussels reported no immediate supply risk from the Iran crisis, but ship traffic through the Strait of Hormuz remained below 10% of normal. QatarEnergy restarted some LNG production, though full recovery depends on shipping. Goldman Sachs cut its TTF price forecast, citing possible volatility if disruptions persist.
NASA wants a long-range drone detection system at Kennedy Space Center as security tightens
Previous Story

NASA wants a long-range drone detection system at Kennedy Space Center as security tightens

Alabama Power coal ash ponds face new scrutiny after report warns of Mobile-Tensaw Delta flood risk
Next Story

Alabama Power coal ash ponds face new scrutiny after report warns of Mobile-Tensaw Delta flood risk

Go toTop