Today: 18 July 2026
TeraWulf (NASDAQ:WULF) Slides 17% as New York Risk Shadows a 77% Out-of-State Open Pipeline
18 July 2026
1 min read

TeraWulf (NASDAQ:WULF) Slides 17% as New York Risk Shadows a 77% Out-of-State Open Pipeline

NEW YORK, July 17, 2026, 18:08 EDT —

  • Shares closed at $18.16, up 1.0% Friday but down 17.3% for the week.
  • A preliminary tally puts 77% of disclosed open capacity outside New York.
  • The Abernathy sale agreement implies a $250 million payment deadline on July 20.

TeraWulf Inc. closed Friday at $18.16, up 1.0%. The shares still lost 17.3% over the week. Regular U.S. trading had ended before publication.

The break followed New York’s July 14 order pausing incomplete state permits for large data centers. It moved the valuation debate from signed leases toward undeveloped power.

The investor question is narrower. A preliminary tally puts 482 MW of TeraWulf’s 2,082 MW open capacity in New York. That is 23%. The other 1,600 MW sits in Kentucky and Maryland.

Company disclosures show the following critical IT capacity:

SiteStateStatusContracted MWOpen MW
Lake MarinerNew YorkOperating438162
Justified DataKentuckyDevelopment4010
Muskie DataKentuckyPlanning and permitting0800
Lake HawkeyeNew YorkPermitting0320
Chesapeake DataMarylandPermitting0800
Total8392,082

The figures are company disclosures, not independently verified construction forecasts.

Lake Hawkeye carries the clearest permit risk. The 320 MW New York project remains in permitting and has no contracted capacity. Lake Mariner already operates. It has 438 MW contracted and 162 MW still open.

Executive Order 62 covers centers able to use at least 50 MW. It holds applications not deemed complete by July 14. Local permits are excluded. No project-specific state determination for TeraWulf was verified.

Rosenblatt analyst Chris Brendler retained a Buy rating and $30 target Wednesday. He called the development “more headline risk than structural.” His view was analyst judgment, not a regulator’s ruling. Blockspace Media

That distinction matters, but it does not remove optionality risk. New standards could add grid charges, capital needs or longer timelines. The order directs state officials to consider those tools.

The largest new lease sits outside New York. Anthropic signed for 401 MW at Justified Data in Kentucky. TeraWulf expects about $19 billion over 20 years. Delivery runs from late 2027 through early 2028.

Chief Executive Paul Prager said the lease “validates our strategy and establishes a long-duration revenue stream.” Rent starts only after each phase is delivered.

The pivot is already visible in revenue. First-quarter HPC lease revenue was $21 million. Bitcoin mining brought in $13 million. HPC supplied 62% of total revenue.

Price action remained rough. Shares fell 7.1% Tuesday and 7.2% Thursday. Friday’s gain recovered little of the weekly loss.

The week ahead brings a cash test. The Abernathy agreement requires a $250 million first installment within 14 days of July 6. That implies a July 20 deadline. Total consideration is about $530 million.

Risks remain. The New York order could delay uncontracted expansion. The Anthropic figure is gross, long-dated contract revenue, not profit. Construction, funding and credit support still shape eventual cash returns.

Next week, investors will watch the Abernathy payment and state permit guidance. Until then, execution on funded, permitted megawatts will carry more weight.

Michał Rogucki is a senior markets reporter at TS2.tech, specializing in stocks, technology and macroeconomic developments. A graduate of Humboldt University of Berlin, he previously worked in investment research and market analysis before transitioning to financial journalism. He covers the trends and events that matter most to investors worldwide.

Stock Market Today

  • TeraWulf Shares Slide 17% After New York Permit Freeze Hits 77% of Pipeline
    July 17, 2026, 7:35 PM EDT. TeraWulf Inc. (NASDAQ:WULF) shares declined 17.3% this week, though they gained 1.0% on Friday to finish at $18.16. New York's order on July 14 halted incomplete permits for large data centers, highlighting risks for uncontracted projects such as the 320 MW Lake Hawkeye site. Just 23% of TeraWulf's 2,082 MW available capacity is located in New York, while 77% is out-of-state, chiefly in Kentucky and Maryland, where the biggest lease-401 MW with Anthropic-provides long-term revenue prospects. Rosenblatt analyst Chris Brendler maintained a Buy rating and $30 price target, calling the permit halt a headline risk rather than a structural concern. Nonetheless, regulatory shifts could add costs or delay timelines. TeraWulf must also meet a $250 million payment due July 20 under the Abernathy sale deal, which will challenge short-term liquidity.
Bank of America (NYSE:BAC) Shares Retain Earnings Momentum with Focus on Rate Sensitivity
Previous Story

Bank of America (NYSE:BAC) Shares Retain Earnings Momentum with Focus on Rate Sensitivity

Commonwealth Bank (ASX:CBA) shares extend gains over rivals as spending slowdown challenges its valuation premium
Next Story

Commonwealth Bank (ASX:CBA) shares extend gains over rivals as spending slowdown challenges its valuation premium

Go toTop